Client |
Project |
Year |
Ferro Metals |
Exchange One Sinter Plant Hood in 24 Hours |
2009 |
MMD – Uramin Swakopmund |
Complete Trial Erection of Mobile Hopper & Primary Crusher Structure (400 Tonnes) |
2009 |
Product, Design & Fabrication |
Supply & Erect Workshop / Building Extension to Prodin’s Main Workshops (±2000 m²) |
2008 |
Middelburg Ferrochrome |
Installation of Spray Cooled Roof & DC Electrode Arm for Furnace M4, Middelburg (Sparcmelt) |
2008 |
Ferro Metals |
Various Patches, Tap Hole Inserts & Repairs to Ferro Metals Furnaces, Witbank |
2008 |
Exxaro KZN Sands |
Manufacture & Install New DC Arc Furnace |
2008 |
Siltech Newcastle |
Manufacture & Install Furnace No. 1, Complete with New Grillage |
2008 |
Anglo Platinum |
Manufacture & Install 200 Tonnes of Additional Heat Protection Platforms |
2008 |
Anglo Platinum |
Partial Rebuild of Furnace after Major Run-Out incl. Steel Platforms & Buckstays |
2008 |
Anglo Platinum |
Complete Rebuild of 6 in line Furnace incl. Demolition, Installation of New Furnace, Installation of New Platform Steelwork, Installation of 3 New Granulation Units, Complete New Piping Installation for Furnace Cooling incl. Pumps, Cooling Ducting, Tanks, Off Gas Ducting etc. |
2008 |
Mogale Alloys |
Supply & Erection of Mogale Alloys DC Arc Furnace Off Gas Treatment Plant |
2007 |
Mogale Alloys |
Supply & Erection of DC Furnace at Mogale Alloys, Krugersdorp |
2007 |
Middelburg Ferrochrome |
Supply & Erection of New DC Arc Furnace, New Electrode Arm, Spray Cooled Roof and Water Cooled Gas Off Take |
2007 |
Richards Bay Minerals |
Replacement of Two Complete Furnace Bus Tube Assemblies |
2007 |
Anglo Platinum |
Maintenance Contract with Smelter for day to day Maintenance on Plant
(2 Year Contract) |
2007 |
Xstrata |
Installation of Furnace D Small Bore Piping & Tundishes at Lydenburg |
2007 |
Xstrata |
Rebuild Assistance to Xstrata Rustenburg during Furnace No. 1 Rebuild |
2007 |
Anglo Platinum |
Rebuild of Furnace Side & End Walls (Copper Waffle Coolers) |
2007 |
Anglo Platinum |
Complete Rebuild of Furnace No. 1 (6 in line) @ Waterval Smelter incl. Structural Steel |
2007 |
Lonmin Platinum |
Demolition & Partial Rebuild No. 1 Furnace |
2006 |
Anglo Platinum |
Side & End Wall Rebuild (Copper Waffle Coolers) |
2006 |
Ongopolo Mining |
Demolition and Rebuild of Reverb Furnace, Tsumeb, Namibia |
2006 |
Zincor |
Complete Demolition and Rebuild of Roaster No. 3 in Springs – Gauteng |
2005 |
Anglo Platinum |
Side and End Wall Rebuild (Copper Waffle Coolers) |
2005 |
Anglo Platinum |
Complete Demolition and Rebuild of Furnace No. 2 (6 in line) |
2005 |
Trans Alloys |
Complete Rebuild of Furnace 5 incl. Electrode Column, Feed Hoppers & Water Cooled Off Gas |
2004 |
Ferro Metals |
Complete Demolition and Rebuild of Furnace 6 incl. Electrode Columns and Feed System |
2004 |
Lonmin Platinum |
Rebuild of Furnace No. 1 Roof |
2004 |
Anglo Platinum |
Side & End Wall Rebuild (Copper Waffle Coolers) |
2004 |
Anglo Platinum |
Side & End Wall Rebuild for Mortimer Smelter |
2004 |
Siltech Newcastle |
Supply & Install new 10800mm Circular Furnace No. 2 |
2004 |